Building bridge tunnel formwork

Ref Price:
Loading Port:
China Main Port
Payment Terms:
TT OR LC
Min Order Qty:
-
Supply Capability:
-

OKorder Service Pledge

Quality Product

Order On-line Tracking

Timely Delivery

OKorder Service Pledge

Credit Rating

Credit Services

Credit Purchasing

Share to:

Product Description:

Building Bridge&Tunnel Formwork:

A compositional steel formwork system mainly used in the building which has regular structure

without beams, the excellent formwork system can make the integral pouring for the wall & slab

easily achieved.


Characteristics:

◆ No assembling, easy operation with formed formwork.

◆ High stiffness, make perfect shape for concrete.

◆ Repeatedly turnover is available.

◆ Widely applied range, such as building, bridge, tunnel, etc.



Send a message to us:

Remaining: 4000 characters

- Self introduction

- Required specifications

- Inquire about price/MOQ

Q:I would like to ask the tunnel hydraulic trolley steel template design is the use of what software
You are talking about the design of the tunnel two lining car software.
Q:How to remove the template of the two lining trolley moving outside the tunnel
The template is removed, the car generally has a fixed track, easy to move. What do not understand, you can secretly I hope to help you!
Q:Tunnel lighting design steps, 2 teachers said to design a template
The pupil is 5 times as fast as the increases, which makes the dark adaptation time to defend much longer. Cone cells can produce or reduce pigment in 10 ~ 12min, and the rod cells are almost 60min need to produce all of the pigment, which makes it very difficult for people to adapt to a very dark environment. How long does it take, depending on the extent of illumination.
Q:Demolition of tunnel bearing formwork for several days
The average temperature of 20 degrees, can be removed for 28 days. High temperature removal time is short, low temperature stripping time longer.
Q:12 meters of the tunnel car, under normal circumstances, one of the two months to be able to cast a few models?
Seven hours after the maintenance of formwork, pouring a every day is no problem, that is to say a month to about fifteen die casting.
Q:Tunnel construction technology and method
5) the construction of open cut tunnel reinforced concrete structure construction is divided into two parts: first, the construction of inverted arch and wall foundation of reinforced concrete, to be part of the concrete reaches certain strength, stripping, cutting hair construction joints, and construction of the upper side wall and arch of reinforced concrete. The inverted arch and wall part of the composite steel formwork, artificial pouring, side wall and arch concrete construction formwork for the internal mold, and molded with combined steel formwork, formwork and external bracing to ensure stable, symmetrical pouring concrete, steel processing plant in processing molding, binding site. The concrete is produced by the automatic metering concrete mixing station, the concrete transport vehicle transportation, the concrete pump into the mold, the insertion type tamping device is compacted, and the arch wall concrete is completed once.6) water proof construction, laying waterproof layer, tunnel construction on the surface of concrete repair chisel flat uneven place to prevent damage of waterproof board. The weld quality of the waterproof board shall meet the requirements. If there is any defect, corrective action must be taken to meet the requirements.7) arch backfilling: Myeongdong vault above maximum backfill height 2m, compaction degree '93% fill in the top-level clay layer of water, the backfill surface of turf.Back fill both sides of the symmetry at the same time, the bottom of the wall filled with 0.5m ~ 1m thick gravel and compacted, and then the use of artificial layered backfill, layer by layer compaction. Careful protection of the waterproof layer during backfilling is not destroyed.The water layer of clay and the side, the slope of the lap is good, close to prevent surface water leakage.
Q:How to set the location of the tunnel trolley,
The next two large positioning along the side mode, re positioning of two small side mode along the point, then turn to check the center point and elevation, if not the positioning deviation is complete, then re adjust the positioning deviation! If you have time to measure the location of the site can be set up, then you do not nail this method, the five points directly to the elevation and mileage can be controlled for a long time
Q:When the two lining of the tunnel is used as the lining concrete of the two, how to lay out the trolley
The next two large positioning along the side mode, re positioning of two small side mode along the point, then turn to check the center point and elevation, if not the positioning deviation is complete, then re adjust the positioning deviation! If you have time to measure the location of the site can be set up, then you do not nail this method, the five points directly to the elevation and mileage can be controlled for a long time
Q:The small side wall of the small side wall and inverted arch in the high speed tunnel
Die casting. Install the inverted L hanger on the side wall.
Q:How to calculate the lining formwork trolley in tunnel construction
In the construction of the tunnel lining template can belong to the low value consumables in accounting, purchasing back into low value, and share in the future cost of 50%, scrap reamortization into 50% of the cost of this method is of low value consumables 55 amortization method; fixed assets, equipment car belonging to the class the asset depreciation period of 10 years. The lining template trolley for a device, rather than separate accounting, and the template should be turnover materials? Added: I engaged in casting model in the low value consumable, car is of course equipment assets added: template is a collar with the repeated use of the low value consumables, which belongs to the class of tools, you can also be classified as turnover materials, but according to the use of reasonable cost sharing principle after ask: you the manufacture of accounting, and it is in the tunnel construction, the construction enterprise to buy trolley. I personally feel that the template should be separated from the car accounting, so more true and accurate. Thank you

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range