• Building Tunnel formwork System 1
  • Building Tunnel formwork System 2
Building Tunnel formwork

Building Tunnel formwork

Ref Price:
get latest price
Loading Port:
China Main Port
Payment Terms:
TT OR LC
Min Order Qty:
-
Supply Capability:
-

Add to My Favorites

Follow us:


OKorder Service Pledge

Quality Product, Order Online Tracking, Timely Delivery

OKorder Financial Service

Credit Rating, Credit Services, Credit Purchasing

Building Tunnel Formwork:

A compositional steel formwork system mainly used in the building which has regular structure

without beams, the excellent formwork system can make the integral pouring for the wall & slab

easily achieved.


Characteristics:

◆ High stiffness, make perfect shape for concrete.

◆ Easy operation, save labor and force.

◆ Fast forming, repeatedly turnover.



Q:The periphery of the tunnel outline has been sealed with steel seal, and can be used as the external formwork when the concrete is poured. The 3 parts of the tunnel are divided into floor, side wall and roof. When pouring, the concrete can only be pumped in the tunnel, the outside of the tunnel is the Pearl River, and the construction can not be carried out outside the tunnel. The roof pouring, only from the bottom to the pump. Question: 1, the roof concrete pouring, how to discharge the air? How to tamper? 2, the tunnel width of 23 meters, you need to do the construction of the seam or after pouring it? Time is pressing, please reply as soon as possible. Good addition score. Thank you。 If you can't see the picture, click this link:
The floor concrete is made by the method of subsection pouring, the length of each section is about 16 ~ 24m, and the construction joint is kept between each construction section. After pouring concrete floor, due to the need for roughly 7 days to meet the design requirements of concrete strength, to remove the floor above the first steel purlin and support. During this period of time can be the first construction of steel bars and formwork works, and then the construction of the outer wall of the leveling layer and the wall of the waterproof layer.
Q:Highway bridge template needs, probably with the thickness of both the construction requirements can be met, and more cost-effective?
Hello, highways, bridges, tunnels, dams, railways and other projects, are generally used in bridge plate 12/15/18MM specifications
Q:Who can give me detailed tunnel construction process
Tunnel construction process, the first branch is a temporary payment, two lining is a permanent support.1, the hole before the edge, the construction of the slope (including drainage, electricity, etc.);2, the construction of large pipe shed3, measurement positioning line;4, drilling, blasting;5, slag, playing anchor, steel, injection (including the initial spray and spray)6, ahead of the anchor (after the pipe section)7, measuring the line;
Q:Loess tunnel construction quality control points
2) the invert, invert the filling layer and dry concrete construction should be concrete accurately, use the template, mechanical tamping compaction. The inverted arch concrete by pumping casting, should use the arch template ensure molding size meets design requirements. The construction of invert arch and filling layer should be completed according to the design of inverted arch concrete construction, the appropriate interval, and then change the proportion of concrete, filling layer of concrete construction;The construction of inverted arch and the cracks and deformation joints should be waterproof treatment according to design requirements, should be in accordance with the relevant provisions of this guide.Invert the overbreak in the allowable range, should be used with the same strength grade of concrete lining casting; overbreak exceeds, should according to the requirements of design and specification of the backfill, shall not use the random hole slag backfill, non intrusive rubble arch section.
Q:The tunnel lining is wood, how should support?
Two concrete tunnel lining, template is used according to the size and shape of the tunnel design custom-made, I-beam welded frame, welded steel plate, known as the "two trolley liner" (hydraulic jack lifting and installation of steel wheel moving on the rail), is generally the length of 9~12m, concrete pouring pump concrete.
Q:Two tunnel lining reinforced concrete template to price behavior can be contracted
Specific price mainly depends on the length of the tunnel, which is the size of the project, and the geological conditions of tunnel is the tunnel construction is now the price of pure artificial price, the specific price or to the bidding price and the construction unit price guide, after all, the project is now basically is the lowest bid, the inevitable choice to compress all fees is the construction unit.If you need to complete the tunnel labor contract price and the cost of all, you can continue to ask questions, hope to adopt!
Q:There are no recycling tunnel templates
If you want another company for the recovery of tunnel two lining trolley, the specific type of price and the address of the template of the trolley that would be able to better the template of the trolley recovery, to play its due value template trolley.
Q:1 tunnel lighting design steps, 2 teacher said to design a template, is not to create a tunnel, and then according to the numerical calculation of what?
Hope to help you. If the human eye to adapt to different levels of illumination, the need to go through three processes, namely, changes in the size of the pupil, nervous system adaptation, cone and rod cells of the photochemical adaptation of pigment.
Q:I would like to ask the tunnel step method excavation, the height of each step is how to divide?
The side ditch construction using composite steel formwork. (1) the temporary facilities of tunnel construction plan layout: in the single ended due to tunnel entrance, temporary facilities of tunnel construction in tunnel exit to the right. The layout for the layout of wind mechanical equipment in the right side of the roadbed export based on the terrain conditions, reservoir located in the left side from the position of about 80m. In the mechanical approach immediately after the entrance of earth excavation construction, roof slope and drainage ditches slope anchor slope reinforcement, well hole digging for. (2): the excavation and reinforcement the mechanical construction, according to the construction method of Subgrade Earthwork excavation, dig to the rock when, in order to minimize the disturbance of the entrance slope and subgrade slope, must adopt the method of weak blasting and presplitting blasting for excavation. The entrance slope using hang net shotcrete reinforcement, to facilitate the safety hole (3). The excavation and support of the shallow section of the surrounding rock of the cave: the construction method adopts the step method, and the advanced grouting bolt is adopted on the stage
Q:What are the driving jobs in the tunnel
Control wire measurement in the cave 5) elevation control survey 6) through survey (7)

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range

Send your message to us

This is not what you are looking for? Post Buying Request

Similar products

New products

Hot products


Related keywords