building tunnel formwork and scaffolding system

Ref Price:
Loading Port:
Tianjin
Payment Terms:
TT OR LC
Min Order Qty:
50 m²
Supply Capability:
1000 m²/month
Inquire Now Customer Service

Contact us by

(1) WeChat
(2) Whatsapp: +8617190086776

OKorder Service Pledge

Quality Product

Order On-line Tracking

Timely Delivery

OKorder Service Pledge

Credit Rating

Credit Services

Credit Purchasing

Share to:

Product Description:

Building Tunnel Formwork:

A compositional steel formwork system mainly used in the building which has regular structure

without beams, the excellent formwork system can make the integral pouring for the wall & slab

easily achieved.


Characteristics:

◆ High stiffness, make perfect shape for concrete.

◆ Easy operation, save labor and force.

◆ Fast forming, repeatedly turnover.



Send a message to us:

Remaining: 4000 characters

- Self introduction

- Required specifications

- Inquire about price/MOQ

Q:Who can give me detailed tunnel construction process
In addition, after blasting excavation contour line must be used with artificial picks excavation, fill hole hole blasting is prohibited, should use the diamond, completes the construction of temporary drainage hole, the pump discharge hole, quartz, mica schist will accelerate the loss of self stability in water immersion, and will accelerate the development of the formation of rock joints, if the groundwater pressure too much damage to increase support.
Q:I would like to ask the tunnel hydraulic trolley steel template design is the use of what software
You are talking about the design of the tunnel two lining car software.
Q:I would like to ask the tunnel step method excavation, the height of each step is how to divide?
The side ditch construction using composite steel formwork. (1) the temporary facilities of tunnel construction plan layout: in the single ended due to tunnel entrance, temporary facilities of tunnel construction in tunnel exit to the right. The layout for the layout of wind mechanical equipment in the right side of the roadbed export based on the terrain conditions, reservoir located in the left side from the position of about 80m. In the mechanical approach immediately after the entrance of earth excavation construction, roof slope and drainage ditches slope anchor slope reinforcement, well hole digging for. (2): the excavation and reinforcement the mechanical construction, according to the construction method of Subgrade Earthwork excavation, dig to the rock when, in order to minimize the disturbance of the entrance slope and subgrade slope, must adopt the method of weak blasting and presplitting blasting for excavation. The entrance slope using hang net shotcrete reinforcement, to facilitate the safety hole (3). The excavation and support of the shallow section of the surrounding rock of the cave: the construction method adopts the step method, and the advanced grouting bolt is adopted on the stage
Q:On the measurement of total station
Slag road slope line, shotcrete receiver measurement, measurement of highway tunnel excavation section, the most important measure is the monitoring and measurement precision of total station but couldn't finish that much. Ha-ha
Q:How to arch the arch concrete pouring
Two concrete tunnel lining, template is used according to the size and shape of the tunnel design custom-made, I-beam welded frame, welded steel plate, known as the "two trolley liner" (hydraulic jack lifting and installation of steel wheel moving on the rail), is generally the length of 9~12m, concrete pouring pump concrete.
Q:What are the driving jobs in the tunnel
Control wire measurement in the cave 5) elevation control survey 6) through survey (7)
Q:How to remove the template of the two lining trolley moving outside the tunnel
The template is removed, the car generally has a fixed track, easy to move. What do not understand, you can secretly I hope to help you!
Q:Demolition of tunnel bearing formwork for several days
The removal time of concrete wall and beam column pouring template is determined according to the strength of concrete, different situations: different removal time of concrete strength of the bottom die and the bracket removal should meet the following requirements:
Q:Concrete construction technology of tunnel roof?
The floor concrete is made by the method of subsection pouring, the length of each section is about 16 ~ 24m, and the construction joint is kept between each construction section. After pouring concrete floor, due to the need for roughly 7 days to meet the design requirements of concrete strength, to remove the floor above the first steel purlin and support. During this period of time can be the first construction of steel bars and formwork works, and then the construction of the outer wall of the leveling layer and the wall of the waterproof layer.
Q:What is the role of the grid steel frame and steel mesh in the power tunnel
Advanced small pipe grouting small catheter with a diameter of 32-50mm steel pipe, the pipe tip and tube holes for special processing. The first row with drill drilling pipe. Row spacing is 30cm, fan shape, elevation of 5 degrees to about 8 degrees. The length is 2.25m, a single fluid grouting (cement) or double grout (cement water glass slurry). Adjust the grouting pressure according to the soil.

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range