Bridge formwork system

Ref Price:
Loading Port:
China Main Port
Payment Terms:
TT OR LC
Min Order Qty:
-
Supply Capability:
-
  • OKorder Service Pledge
  • Quality Product
  • Order Online Tracking
  • Timely Delivery
  • OKorder Financial Service
  • Credit Rating
  • Credit Services
  • Credit Purchasing

Add to My Favorites

Follow us:

Building Bridge Formwork:

A compositional steel formwork system mainly used in the building which has regular structure

without beams, the excellent formwork system can make the integral pouring for the wall & slab

easily achieved.


Characteristics:

◆ No assembling, easy operation with formed formwork.

◆ High stiffness, make perfect shape for concrete.

◆ Repeatedly turnover is available.

◆ Widely applied range, such as building, bridge, tunnel, etc.



Q:What is the concrete construction of the tunnel invert
It is not required to ensure the appearance of the concrete, is the high pressure jet, the rapid solidification type.
Q:I would like to ask the tunnel step method excavation, the height of each step is how to divide?
Tunnel excavation adopts mechanical construction, tunnel excavation using simple self assembling drilling trolley, millisecond detonator, in order to improve the effect of smooth blasting around the eyes, around the eye using special Nonel detonation. Tunnel outlet using muck loader, dump truck with transport ballast. Two tunnel lining concrete use of the length of integral pouring formwork trolley 12M, concrete mixing station in centralized mixing, concrete transport vehicle transport pump into the mold.
Q:What are the reasons for the two lining concrete lining of the tunnel?
(4) improper concrete mix, segregation, depending on the template part of the lack of slurry or template serious leakage;(5) no watering wood template wet, water bonding or early form removal, Chaimo missing edge off angle, resulting in reinforcement.
Q:Who can give me detailed tunnel construction process
Tunnel construction process, the first branch is a temporary payment, two lining is a permanent support.1, the hole before the edge, the construction of the slope (including drainage, electricity, etc.);2, the construction of large pipe shed3, measurement positioning line;4, drilling, blasting;5, slag, playing anchor, steel, injection (including the initial spray and spray)6, ahead of the anchor (after the pipe section)7, measuring the line;
Q:Loess tunnel construction quality control points
The main points of concrete construction of tunnel invert:1) should advance concrete arch wall concrete construction of inverted arch arch and the construction should be removed before water, slag and other sundries, false
Q:The tunnel lining is wood, how should support?
The excavation of the tunnel face, slag, to the primary support system, first hit the bolt, then use steel or steel made of steel, installation support in tunnel contour, and then sprayed concrete (poor surrounding rock hanging steel mesh, then sprayed fiber concrete).
Q:In the process of tunnel construction, two kinds of formwork system should be adopted in the construction of the two lining concrete. Q: what is the template trolley?
Generally, a plurality of arc and straight steel die!Normal lining trolley
Q:The periphery of the tunnel outline has been sealed with steel seal, and can be used as the external formwork when the concrete is poured. The 3 parts of the tunnel are divided into floor, side wall and roof. When pouring, the concrete can only be pumped in the tunnel, the outside of the tunnel is the Pearl River, and the construction can not be carried out outside the tunnel. The roof pouring, only from the bottom to the pump. Question: 1, the roof concrete pouring, how to discharge the air? How to tamper? 2, the tunnel width of 23 meters, you need to do the construction of the seam or after pouring it? Time is pressing, please reply as soon as possible. Good addition score. Thank you。 If you can't see the picture, click this link:
Concrete construction technology of tunnel roof:Due to the main roof, the floor of a large amount of concrete pouring, consider the construction period and other factors, the site is equipped with 2 sets of automotive pump or HBT60 pump and 300m Phi pipe and a variety of accessories.
Q:The tunnel structure of plastic mould
In the use of the whole tunnel mode is not as flexible as semi tunnel mode, the lifting equipment requirements are higher, it is gradually being semi tunnelMode substitution.
Q:When the tunnel fight, there is no provision to fight how many meters left, only by one of the construction
Fixed strip: the use of additional reinforcement fixation; special fixture fixed; the wire and the fixed template (Figure 2).

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range

Send your message to us

This is not what you are looking for? Post Buying Request