Support grouting material
- Loading Port:
- Qingdao
- Payment Terms:
- TT OR LC
- Min Order Qty:
- -
- Supply Capability:
- 2000吨 m.t./month
OKorder Service Pledge
OKorder Financial Service
You Might Also Like
AJ support grouting material
Category: reinforced mortar series
AJ support grouting material is a kind of high strength cementitious material by, many kinds of additive composite and selected aggregate by the special process of preparation, a seat slurry has the characteristics of high fluidity, no shrinkage, early strength and high strength etc..
* use products:
AJ support grouting material suitable for all kinds of machinery, electrical equipment (heavy equipment, high-precision grinding machines) produced a grouting and base slurry pier.
* technical indicators:
Project
Index
Compressive strength (MPa) >
The 3 day
30
The 28 day
50
Expansion (mm)
200
Expansion rate (1 days)%
0.020
Bleeding rate%
0
* construction points:
(a) the foundation treatment and formwork:
1, cut surface concrete foundation wool, and clean them off. The adhesive member together with the seat size (such as steel plate) will rust and
Remove oil etc..
In 2, water base slurry before 4 hours, on the surface of the concrete foundation applied to moist, when the water is not water.
3, supporting baffle should be tight, to prevent the leakage of slurry.
(two) AJ support Grouting grouting material:
1, the amount of water per bag (25kg): water ratio of 4.0~4.5kg mixing with water, such as the construction does not require greater fluidity can be
We should reduce the amount of water used.
2, the mixing procedure: add a prescribed amount of water into the blender in the mixing barrel, a part of base slurry into the barrel stirring diluted, and then
The residual material into the mixing, the time from beginning to end should be controlled within a minute or so.
3, stirring, leaves should be along the barrel around the upper and lower left move slowly, so that the bottom of the barrel and the barrel wall adhesion dry to mixing; stirring
Leaf blade not to mention above base slurry liquid level, in order to avoid the air with seats in the furnish.
4, the mixing base slurry clay good should be timely watering. The time of irrigation, as far as possible from one side of the injection, to facilitate discharge plate and concrete foundation
The air between the. When necessary, can use the bamboo slice tool guide. Water after the start must be continuous, not interrupted.
* mixing machine:
The double handle electric drill, power is larger than 450W, the rotational speed is greater than or equal to 500r/min.
The mixing blade made of delta =1.2mm thick steel plate, blade diameter of 150mm, the stirring rod diameter of 12mm bar.
* note:
Field use, is strictly prohibited in the clay in the incorporation of any additive, additive. Not and other manufacturers of similar products mix, to ensure the engineering quality.
Unit maintenance:
1, with wet straw bags or cloth covers the base slurry have been watered well, and water conservation, 2-6 times a day.
2, curing temperature is over 15 DEG C, the 7 day of the maintenance period. If the temperature is low can be appropriately extended maintenance period.
3, the need to take preservation measures in winter construction.
* stripping:
Formwork shall be completed for 24 hours in the water, after stripping continued maintenance.
Packaging and storage:
Packaging specifications for 25kg + 0.5kg, composite paper bag lined with plastic bag. Stored in a dry, cool place, without moisture preserved stored for a period of three months. Extended need re examination, qualified before use.
A, grouting material product introduction:
Grouting material with special cement as binder, selected high strength materials as aggregates, with high flow, micro expansion, anti segregation and other material prepared.
The product has good gravity flow, rapid hardening, early strength, no shrinkage, expansive; non-toxic, harmless, non aging, on water quality and no pollution to the surrounding environment, self sealing good, rust and other characteristics. In the construction aspect with reliable quality, reduce the cost, shorten the construction period and convenient advantages. To fundamentally change the equipment base force, so that the whole load uniformly bear device, so as to satisfy all kinds of machinery, electrical equipment (heavy equipment of high precision grinder) installation requirements, is the ideal filling material without pad mounted era.
Two, the scope of application:
Grouting material is mainly used for: the anchor bolt anchor, runway repair, nuclear power equipment, Luqiao fixed reinforcement engineering, machine base, steel structure and foundation with export, equipment foundation grouting, planted two times buried reinforced, concrete structure reinforcement and reconstruction of old concrete structure, crack control, electrical and mechanical equipment installation, track and installation of steel structure, static pressure pile engineering piles, structure of the wall thickening and repair the leakage, all kinds of foundation engineering collapse grouting and various repair engineering etc..
Model No. | Compressive strength(MPa) | Vertical expansion rate (%) | Fluidity | Grip strength Round steel. MPa | The bleeding rate(%) | Remarks | ||||
6h | 1d | 3d | 28d | 1d | The initial fluidity | 30min Fluidity retention value | 28d | |||
Universal type | -- | ≥15 | ≥30 | ≥70 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
High strength | -- | ≥30 | ≥40 | ≥70 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
Early strength type | ≥20 | ≥30 | ≥40 | ≥60 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
High early type | ≥22 | ≥30 | ≥40 | ≥70 | ≥0.02 | ≥260 | -- | ≥4.0 | ≤1.0 | |
Super flow type | -- | ≥15 | ≥25 | ≥50 | ≥0.025 | ≥300 | ≥250 | ≥3.5 | ≤1.0 | |
High temperature resistant type | -- | ≥22 | ≥40 | ≥60 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 |
The engineering design reference: anchor bolts for anchoring cement
380 | 340 | 290 | 270 | |||
The maximum set size(mm) | ≤4.75 | >4.75and≤16 | ||||
Fluidity(mm) | The initial flow | ≥380 | ≥340 | ≥290 | ≥270* | ≥650** |
30min retention value | ≥340 | ≥310 | ≥260 | ≥240* | ≥550** | |
Vertical expansion rate (%) | 3h | 0.1~3.5 | ||||
24h and 3H expansion difference | 0.02~0.5 | |||||
Compressive strength(Mpa) | 1d | ≥20 | ||||
2d | ≥40 | |||||
28d | ≥60 | |||||
There is no corrosion of reinforced | NO | |||||
Qinshui rate (%) | 0 |
The engineering design reference:
Cement based grouting material choice for anchoring bolt anchor:
The spacing of the surface of the bolt and the hole wall(mm) | Cement based grouting material categories |
15~50 | 340、290 |
50~100 | 290、270 |
>100 | 270 |
Cement based grouting material selection with two grouting:
Filling layer thickness(mm) | Cement based grouting material categories |
5~50 | 380 |
20~100 | 340 |
80~200 | 290 |
>200 | 270 |
Four, product characteristics
"Pour 1-3 days after high early strength was as high as 30Mpa, shorten the construction period.
Since the flow field - just add water, stir, direct filling equipment foundation, mortar self construction, free vibration, ensure the grouting construction of long distance without vibration.
Casting body is used for a long time without shrinkage / micro expansion, to ensure that equipment and basic close contact, no shrinkage between the foundation and foundation, and appropriate expansion of the compressive stress to ensure the long-term safe operation of equipment.
* anti oil leakage after 30 days soaking its strength in the oil increased by more than 10%, molding, compacting, impermeability, adapt to the base oil of environmental protection. * durability 2000000 times fatigue test, 50 times freeze-thaw environment test strength has no obvious change.
"Good weather -40 to 600 DEG C is safe for long-term use
* low alkali corrosion resistance of the strict control of raw material of alkali content, suitable for alkali aggregate reaction inhibiting requirements engineering.
Five, the use of methods
1 Foundation Treatment
Cleaning equipment based on the surface, there shall be no stone, laitance, dust, dirt and other debris demoulding agent. Before grouting 24h, fully moisten the surface of equipment foundation. Before grouting 1H, should be sucked up water.
2 determine the grouting method
According to the actual situation of equipment base, selection of grouting method of corresponding flow, because of its good performance, in general, with "weight grouting" can, will paste directly from template export poured into slurry, completely rely on the self weight to leveling and filling the whole filling space; if a large area, especially the complex structure of perfusion or a very small space and distance, can use "high funnel method grouting" or "pressure grouting, grouting method" to ensure that the slurry can be fully filled every corner.
3 formwork
According to the grouting and grouting construction diagram determined by the way of support design templates, template location elevation should be higher than the equipment on the base surface of at least 50mm, template must support of a tight, firm, to prevent loosening, leakage.
The 4 stirring grouting material
According to the water feed products recommended certificate than the amount of water, mixing water should be used to drinking water, the water temperature to 5 ~ 40 degrees is appropriate, can use mechanical or manual stirring. By mechanical mixing, stirring time is generally 1 to 2 minutes. The use of artificial mixing, should first join 2/3 with water and stir for 2 minutes, then add the remaining water to continue to stir until evenly, standard consistency water volume is 12%-14%.
5 grouting
Grouting construction should meet the following requirements:
(1). The slurry should be poured into the side, until the other side overflow until, in order to facilitate the discharge between the device frame and concrete foundation of air, so that the filling, not from the four sides of the grouting.
(2). The grouting after the start, must be continuous, not interrupted, and should be possible to shorten the filling time.
(3). During the grouting process should not be vibrated, when necessary, available bamboo laths were pulling the diversion.
(4). Each filling layer thickness should not exceed 100mm.
(5). The grouting long equipment or track foundation, should use the segmental construction. The length of each section is appropriate in 10m.
(6). The grouting process such as the discovery of surface bleeding phenomenon, can dispenser a small amount of dry material, sucking up water.
(7) for the foundation of equipment grouting layer thickness is greater than 1000mm in large volume, stirring grouting material according to total ratio 1:1 join 0.5mm stones, but the required test for determining the groutability can not meet the requirement.
(8). The equipment foundation grouting is completed, should be removed part shall be treated in the grouting layer before the final setting.
(9). In the grouting construction process should be avoided until the mold, filling layer by vibration and collision, so as not to damage the pending grouting hard layer.
(10) the horizontal distance between the template and the equipment of the base should be controlled at around 100mm, in order to facilitate the grouting construction.
(11) slurry filling in phenomena such as appearance, should be timely treatment.
(12) when the equipment foundation grouting amount is larger, should adopt mechanical agitation mode, in order to ensure grouting construction.
6, maintenance
(1) after grouting is finished. In 30 minutes, immediately spray curing agent or covered with plastic film and affix rockwool were maintenance, or in the grouting layer after the final set immediately sprinkler wet maintenance.
(2) in winter construction, conservation measures shall be in accordance with the "reinforced concrete construction acceptance norms" (GB50204) the relevant provisions.
(3) at different temperature curing time and removal time schedule
Daily minimum temperature (c) time of stripping (H) curing time (d)
-10 - 0 96 14
0 -5 72 10
5- 15 48 7
≥15 24 7
- Q: What materials do the bathroom waterproof anti-leakage ah? Do not use cement directly?
- Direct use of cement not, the cement itself is not waterproof, the bathroom waterproof material is the best high-waterproof waterproof and general-purpose waterproof material
- Q: 1 square mull retaining wall is equal to how many square stone
- Under normal circumstances, the masonry wall mortar label between the M5-M. the construction of stone concrete, the participation of the rough stone is generally about 25% of the volume, the amount of data provided above the amount of one stone needs 1.15m ?. In the use of sand, mud content of less than 3% of the sand in the preparation of mortar, per cubic meter of stone wall with the theoretical mix should be used 60-120kg cement, the actual operation of the cement: sand weight ratio of about 1: 5.5-6 can To ensure that M5 cement mortar strength test qualified construction attention to conservation. Five stone side of the sand, cement two packs.
- Q: Whether the mortar waterproofing agent needs to be sampled for inspection
- The format of the power of attorney for each place is different, but the main content is basically the same
- Q: Have you heard of waterproof building materials? What are the characteristics of who
- Building materials can be divided into structural materials, decorative materials and some special materials
- Q: 10 tons of dry powder mortar production line and supporting the need to invest how much money
- 2-15 tons, 3-5 minutes mixed with a batch of materials, remove the time to feed, an hour to do 8-10 tons no other investment, if you want to engage in a small factory, to hang individual card, if You want to engage in some formal, that But also with the experimental equipment, but also to the building materials for the record, basically on these, if you do not understand, please keep abreast of the exchange
- Q: Car wash center of the wall, to be waterproof do not know how to deal with the right!
- I have done this friend, if the sticky tiles, may not apply, because the car wash when the bumps, if the sticky tiles do not need to do waterproof, that tiles is waterproof, as long as the tile gap with tiles to deal with like , It is recommended that you still do cement mortar waterproof method is to use the new green high concentration mortar waterproofing agent, against the concrete inside the sand, and then wipe a layer of gray on the wall ok. If you use other products, it is easy to cause wall cement layer off,
- Q: What is the best bathroom waterproof material? Bathroom is a membrane or paint ah, what good manufacturers recommend more
- Hello ~ bathroom waterproof recommended the use of js waterproof coating, bathroom to be facade brushing, that is to say the wall needs to do waterproof, brushing height of 1.5 meters. Corner (right angle) brushing should be done before the corners of the deal, it is best to use plugging treasure or mortar to do arc chamfer, and use grid cloth to do local enhancement. For the purchase of the product, you can go to the local regular building materials market to buy, Rainbow's private building agents for your details of the ~
- Q: What are the characteristics of EVB thermal insulation fireproof dry mortar? Guangxi
- low cost: can be directly applied to the dry base surface, leveling layer and insulation layer into one, significantly reducing the overall construction costs, cost-effective
- Q: 18 layers of high-rise, frame-shear structure, the northern coastal areas, the external walls of real stone . wall materials with no burning hollow brick good? Do you want to use a red brick or a gray brick on every floor when you build a wall? If the direct puzzle does not have any impact, will not moisture it? What are the consequences of living in the world? . external wall insulation What is more popular in the north, the use of insulation board (such as polystyrene board) and insulation mortars have their own advantages and disadvantages? Also do the external insulation, the house is also used for insulation it? Is not finished pouring the wall after leveling is the rough room? More
- As for the red brick base, did not find the standard support, it is estimated that the basic leveling with the red brick and hollow brick for moisture is not much difference, I would like to consider moisture
- Q: Because before the paste with cement mortar, easy to fall, would like to ask if there is no other way to add the problem: it is better to say that the more detailed point
- Because before the paste with cement mortar, easy to fall, would like to ask if there is no other way to add the problem: it is better to say that the more detailed point
Send your message to us
Support grouting material
- Loading Port:
- Qingdao
- Payment Terms:
- TT OR LC
- Min Order Qty:
- -
- Supply Capability:
- 2000吨 m.t./month
OKorder Service Pledge
OKorder Financial Service
Similar products
Hot products
Hot Searches
Related keywords