steel props of C

Ref Price:
Loading Port:
China Main Port
Payment Terms:
TT OR LC
Min Order Qty:
-
Supply Capability:
-

OKorder Service Pledge

Quality Product

Order On-line Tracking

Timely Delivery

OKorder Service Pledge

Credit Rating

Credit Services

Credit Purchasing

Share to:

Product Description:

Detailed Product Description



suspended slab formwork

slab form work

concrete slab formwork



150 Aluminum Frame Early Dismantling Slab Formwork With Adjustable Prop


Description:

1. Brief introduction
Especially for projects with a large number of similar applications and open facades, Alu-slab system is the right solution. The panel is end product, no assembling on site and it is easily to build, ease of application, more important thing is, the panel is light weight, a dead lift is achieved, save time and effort.

150 Aluminum Frame Slab Formwork System With Adjustable Prop

2. Competitive advantage

① Light weight but high load bearing capacity
The panels could be transported by manual work so that it greatly reduces the aggregate cost, accelerates the erection speed, and all in all increases the aggregate benefit.

②Quickly turnover of slab panels
The early dismantling prop system speed up the turnover of the panels, minimize the investment, lower the cost, improve the working efficiency, and shorten the project period under the precondition of keeping the concrete structure and safety uninfluenced, in line with the erection requirement and ensuring the project quality.

③Cost effective with early dismantling prop system.
This early dismantling system is simple, safe and fast, saving at least 50% percent of your construction time.

3. Applications

150 Aluminum Frame Slab Formwork System With Adjustable Prop

150 Aluminum Frame Slab Formwork System With Adjustable Prop


Send a message to us:

Remaining: 4000 characters

- Self introduction

- Required specifications

- Inquire about price/MOQ

Q:How to reinforce the lower part of the construction elevator on the garage roof
The coefficient is close to 5 tons 50KN lifting conditions consider the edge pressure of the pressure to be more load release plate can put beam line can arrange the column even if the column double foundation
Q:How many tons of steel support
The excavation of the foundation pit is divided into 3 large mechanical excavation and the 1 Artificial Excavation of the bottom of a total of 4 steps: (1) the first layer of the main use of short arm excavator excavation, excavation to the ground under the 0.9m, the erection of the first support.
Q:What are the characteristics of steel frame bracing system
Steel frame bracing system has the same characteristics. Should be in the steel structure after the heat will quickly lose strength and stability, steel structure of the fire is also a feature of heat.
Q:Steel support lease 700 tons, the total amount of money per day
The key is to see this steel support lease fee 700 tons is to let you rent a few days, with the rental fee divided by the total number of days to be able to calculate how much the daily rent.
Q:What is the maximum value of the support settlement on the beam
(!) in accordance with the "reinforced concrete beam" design specification for hydraulic concrete structures and the "standard methods for testing of concrete structures", produced a total of $reinforced concrete beam, the beam length! "'% & section size!' ($& $&& 'concrete labeling for the quantity of materials per * *). Party and relevant index table! + beam reinforcement figure! + molding, maintenance to $, reached the design strength requirements of concrete materials per square meter +! And related indexes of -./+! 0123456718 9:/29 15189; <98151 =.5182.>6;'., 2<, 1?; <98151 = 5419; each party (concrete materials A3 'B *) - @ index grade of cement cement fine aggregate coarse aggregate average compressive strength of @ CD. @ 9" slump "$" E F! "" GG! *G! H FHI% *J "$"! The reinforced concrete beam reinforcement figure K23+! LA1594; = 812<=; 1<5 = 891; < 8151 / 8.9; 1 'sticky ($) bonding agent
Q:What is the size and wall thickness of the steel support inside and outside?
Press locking and fastening connection KGB wall thickness and JDG are very different,JDG in addition to 16 of the pipe wall thickness of 1.2, the rest are all of the 1.6.KGB tube wall thickness and pipe size. More than 16 also have more than 1.2, and more than 1 of theKBG metal threading pipe and JDG metal threading pipe are widely used in the construction of electrical engineering of 1kV and below, because of its advantages such as convenient construction, low cost, superior performance, complete specifications and complete products
Q:What are the testing items of steel support
Strength and stiffness: steel braces must have sufficient strength and stiffness.
Q:The exterior package aluminum plate, with steel support, about how much money.
General should be between 450-600 yuan / square meters. Only the price in this range, with a real to
Q:Please steel structure of the steel support what needs to be done, where to find
If you understand it correctly, you are asked about the steel support component anti-corrosion coating:
Q:Subway construction of steel support needs qualification
Qualification required.The subway is referred to as the "underground railroad", city rail transit system in narrow sense refers to operation of the underground.

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range