• Construction Hoist Materail and Human Lifting System 1
  • Construction Hoist Materail and Human Lifting System 2
  • Construction Hoist Materail and Human Lifting System 3
  • Construction Hoist Materail and Human Lifting System 4
  • Construction Hoist Materail and Human Lifting System 5
  • Construction Hoist Materail and Human Lifting System 6
Construction Hoist Materail and Human Lifting

Construction Hoist Materail and Human Lifting

Ref Price:
get latest price
Loading Port:
China main port
Payment Terms:
TT OR LC
Min Order Qty:
1 unit
Supply Capability:
100 unit/month

Add to My Favorites

Follow us:


OKorder Service Pledge

Quality Product, Order Online Tracking, Timely Delivery

OKorder Financial Service

Credit Rating, Credit Services, Credit Purchasing

 

Structure of Construction Hoist Description

 

The general building hoist manufactured by our company have the features as good quality, long life, wide application range and convenient for maintenance. The gearing adopted bearing,enameled cable, and oil seal. The electric parts adopt products from worl renowned manufacturers such as Schneider, Siemes, and LG. The racks and pinion adopts specal material and heat-treatment technique, which prolong the life of these parts. The steel structure uses quality steel from famous domestic manufacturers. The surface of the structure can apply paint-spray, parkerizing baking finish or hot galvanizing processing according to users requirments. The cage can be produced and decorated by aluminum molded board, punched-plate or figured aluminum board.

 

Main Features of Construction Hoist

 

1. The recomended cage dimension(L*W*H)(m): 2.0*1.0*2.5, 2.5*1.0*2.5, 2.5*1.3*2.5, 3.0*1.5*2,5, 3.2*1.5*2.5, 3.8*1.5*2.5, 4.0*1.5*2.5, 4.2*1.5*2.5 etc. We can also manufacture cages of other size according to the user.
2. The cage and the door material can be aluminum molded board, punched-plate, figured aluminum board or other type according to yout requirements.
3. The mast section and the tie-in surface can adopt paint-spray, or hot galvanizing processing.. 

Construction Hoist Specifiction 

SC series product also has special design, such as reinforced guide rail with cross-section of 800mm, inclined type, special for cooling tower, etc. All the double cage building hoist can be changed into single cage type,

 

  TypePayload(kg)Lifting Speed         (m/min)Motor Power(kw)Safety Device
Twin Cage HoistNo CounterweightSC100/1002*1000332*2*112*SAJ30-1.2
SC120/1202*1200332*2*112*SAJ30-1.2
SC160/1602*1600332*2*112*SAJ30-1.2
SC200/2002*2000332*3*112*SAJ40-1.2
SC250/2502*2500332*3*112*SAJ50-1.2
SC270/2702*2700332*3*152*SAJ50-1.2
SC300/3002*3000332*3*152*SAJ50-1.2
SC320/3202*3200332*3*152*SAJ50-1.2
With CounterweightSCD200/2002*2000332*2*112*SAJ40-1.2
SCD250/2502*2500332*2*112*SAJ50-1.2
SCD270/2702*2700332*2*152*SAJ50-1.2
SCD300/3002*3000332*2*152*SAJ50-1.2
SCD320/3202*3200332*2*152*SAJ50-1.2

 

Images of Construction Hoist

 

 

Construction Hoist Materail and Human Lifting

Construction Hoist Materail and Human Lifting

Construction Hoist Materail and Human Lifting

Construction Hoist Materail and Human Lifting

Construction Hoist Materail and Human Lifting

 

FAQ of Construction Hoist

 

Q: What is the main structure of building hoist? 

A: The P/M construction hoist mainly contains metal structure, driving system, electrical control system, cable guide & protection system, electrical top crane and safety device.  

Q: What is the meaning of the building hoist’s code?

 A: Take SC200/200 for example: “SC” stands for rack and pinion hoist, “200/200” stands for double cage and capacity is 2 tons per cage. “SC200” stands for single cage and capacity is 2 tons. 

Q: What is the dimension of the cage? 

A: Normally the cage dimension is 3X1.5X2.5M (L/W/H) for 2t type hoist. Details should be checked according to our quotation sheet. Also, the size can be customized according to the factual site condition.  There are two doors (entrance& exit doors) for each cage, It can be produced as up & down sliding or ramping model for safety and convenience.

 

Q:6 layer of brick and concrete construction project, have tower crane still need construction elevator?
Tower crane is used for heavy lifting, long pieces, small machinery and materials must be used in the construction elevator.
Q:How does the elevator operate
One must first understand the basic structure of the elevator, function, operation and safety protection measures for each elevator, so each new elevator operation need to carefully look at elevator operation manual! 2 each elevator switches in eye-catching position, the first thing to know to control the power box, and stop buttons and effective protection switch, it is helpful for you in the process of operation, have safety emergency measures! 3 each elevator has the control box, it has indicated the direction and floor indicator, if your operation is simple and easy lift, it is not a lot of protection measures, only up to the threshold, sometimes may malfunction, press in operation had better stop, make sure someone wrong operation or accident happen! 4 as for how to increase the security of the original equipment and measures, can reach Ann and suzhou mechanical and electrical technology department contact, they have free professional technical support and solutions!
Q:The safety officer shall be responsible for the work of the construction elevator
(1) the use of dual-use functions of the construction elevator, the installation and removal of the professional personnel issued by the competent department of construction administration shall be undertaken by the professional personnel. The personnel who have passed the training, qualified for the examination and obtained the certificate of the post shall be operated and repaired. (2) the capacity of the concrete base culture cooperation should not be less than 150kPa, the tolerance of 10mm and the drainage facility should be allowed. The distance between the guide bracket of the elevator and the wall of the building should be suitable, and the smoothness should be stable. (3) the lifter is used to control two directions, and the vertical control is 0.05%. Each floor shall have a platform, a passage, a fence and a protective door. No obstacles can be found. (4) the elevator that is installed in a dark place, and the passage shall be illuminated and a floor display lamp and floor number; A closed barrier should be set up in the well. The elevator shall be subject to acceptance by the technical director and the relevant departments, and shall be tested by the crash and shall be used in the rear. (5) in the use of or during the use of the elevators, the manufacturer or designated unit shall conduct the debugging and maintenance and verification. The lifter should undergo a fall test every three months and the fall test should be adjusted when the fall test exceeds 1.2 m. Every time it falls, the receiver should be repaired once.
Q:Safe use of construction elevator
In the case of passenger and carriage, the loading shall be uniformly distributed, and the overload shall be strictly prohibited. When the elevator runs to the top and lowest levels, it is strictly forbidden to stop at the collision or lower limit. 7. The driver for leaving hanging basket and while going off work, should be hanging basket fell to the ground, to cut off the total power supply, and the door is locked point, prevent other undocumented workers start the hoisting cage without authorization. Wind up above 6, should stop using the elevator and bring the cage down to the ground. There must be good protection on both sides of the transportation channel. Floor door should be in a normally closed state, its height should conform to the requirements of the specification, anyone shall not open or head out of the door, when the floor door open, the driver shall not start the elevator. Ensure that the communication device is in good condition and the driver should be able to start the lift after confirming the signal. The driver should immediately execute any emergency stop signal on the floor of the operation. The elevator should be installed on a separate ground protection and lightning protection device. It is strictly forbidden to do maintenance work under the condition of the elevator. If maintenance is required, the power supply must be cut off and the sign of "check in, shut off" will be hung in a prominent place.
Q:Are there any good signs in the construction elevator door
It is forbidden to climb, construction lift operation procedure, limited number of passengers, no power cuts
Q:Gear rack driven
Driven by two or three worm gear reducers, the ladder cage is a load bearing unit, and gravity is carried by a rack. At rest, the force point is in the meshing of the gear and rack.
Q:Why is the construction elevator open on one side and the other on the other
The two-door design is designed for the safety of the operator. In the discharge mouth, if you set up a single door, a large portion of your body will be exposed outside, causing falling damage.
Q:The maximum allowable deviation of the vertical is the vertical degree when the construction elevator is installed
5 kinds of circumstances. 1: the height of the elevator guide frame is less than 70 meters, and the vertical deviation should not be greater than one in 1000 of the height of the guide frame. (assuming the rail frame is 70 meters high, the deviation cannot be greater than 70mm) 2: the rail frame is greater than 70 meters and is less than 100 meters, and the deviation is less than or equal to 70 mm. 3: the guide frame is larger than 100 meters and is less than 150 meters. The deviation is less than or equal to 90 mm. 4: the guide frame is larger than 150 meters is less than or equal to 200 meters. The deviation is less than or equal to 110 mm. 5: the guide frame is greater than 200 meters, and the deviation is less than 130 mm. This is based on the requirement of 5.2.2.1 from GB10054 to 2005. (it used to be a direct copy.)
Q:Safety device for construction elevator
Many 1, 2, upper and lower limit for safety device 3 TDD, extreme limit 4, buffer spring 5, has threshold position switch, single threshold position switch 7, 6 top and limit switch 8 TDD, enclosure door lock 9, lock line 10, has locks There are a lot of electrical safety protection
Q:Is the elevator detail a construction plan? Do you have a detailed picture of the elevator?
The construction diagram of the elevator appears to be a qualified elevator construction unit

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range

Send your message to us

This is not what you are looking for? Post Buying Request

Similar products

New products

Hot products


Related keywords