• Detachable Construction Hoist System 1
  • Detachable Construction Hoist System 2
Detachable Construction Hoist

Detachable Construction Hoist

Ref Price:
get latest price
Loading Port:
Tianjin
Payment Terms:
TT or LC
Min Order Qty:
-
Supply Capability:
-

Add to My Favorites

Follow us:


OKorder Service Pledge

Quality Product, Order Online Tracking, Timely Delivery

OKorder Financial Service

Credit Rating, Credit Services, Credit Purchasing

SC200 detachable construction hoist

The machine is made into five parts and connected together by bolts and nut, which is very convenient for installation in elevator shaft.

During the installation of machine in the elevator shaft, the space is very small. Due to the small entrance for elevator, the building

hoist has to be disambled into pieces, then it is very easy to move and convenient to assamble.

This machine has features as below:

1 Lifting capacity: 3000kg

2 Single cage

3 Lifting speed: 0- 60m/min, adopting Schneider inverter or Yasakawa Inverter

4 Motor  power: 3x15kw

5 Mast section size: 650x650x1508mm, pipe diameter 76mm

6 Maximum lifting height: 250m,

7 Cage size: 3.2x1.5x2.5m or tailored as per clients' requirements.

the cage size can be changed to be 2.4m by removing two parts away from the machine. Also the base enclosure can be adjusted to adapt

the change of cage size.

8 Comparing with the traditional worm-gear transmission, this new driving system adopts directly connection motor & reducer, which improves

the driving efficiency, reduce the consumptions of energy.


If you have any difficulties in your construction about material lifting ,we can provide tailored design.

Construction lift with Interver:

CharacteristicsModelRated LoadingLifting SpeedMotor Power
 
 
Double Cabin
 
 
Low-speed
SC200/200D 2 × 2000kg0-36m/min2 × (3 × 11kw)  2 × (2 × 13kw)
2 ×(2 × 15kw)   
SC100/100D 2 × 1000kg0-36m/min2 × (2 × 11kw)
 
Mid-speed
SC200/200Z 2 × 2000kg0-60m/min2 × (3 × 15kw)
SC100/100Z 2 × 1000kg0-60m/min2 × (2 × 15kw)
 
Single 
Cabin
 
Low-speed
SC200D    2000kg0-36m/min3 × 11kw
2× 13kw
2× 15kw
SC100D    1000kg0-36m/min2 × 11kw
 
Mid-speed
SC200Z    2000kg0-60m/min3× 15kw
SC100Z    1000kg0-60m/min2 × 15kw

 

 

 

 

Q:Why do you ask the construction elevator to be a certain distance from the structure? Is very close to if not you can not bother to do delivery channel security protection or something, out of the elevator out directly, and attachment should be able to get more easily, to solve. Thank you very much!!
The distance between the moving parts and the building and the fixed construction equipment shall not be less than 0.25 m. The main thing is to prevent the person from the point of view. For example, workers are on the third floor to look down, hanging cage, where is the result now hanging basket is go down from the fourth floor, if not the 25 cm, likely to brush "cut".
Q:Does the new approach builder need a localizer test report
Need, not for safety device testing qualified report, inspection agency will not issue the inspection report, in the construction of elevator installation supervision and inspection report, there is a specifically for, for safety device must have testing qualified report, to be certified.
Q:How to adjust the weight limit of the construction elevator
You're talking about a weight monitor! There are a lot of models and not a good idea.
Q:How do construction suspension scaffolding be handled in the people's elevator?
Suspension of steel and steel is used to avoid the elevator, and it is OK to encrypt it on both sides of the elevator
Q:Why is the construction elevator not up to the roof
The free end of the construction of the lift height is only 7.5 meters high, general construction elevator drive now is the case, so the hoisting cage height and drive around 4.5 meters high, the other national standard construction elevator ceiling limit moves, drive above about 1.8 meters away from the top of the rails. So it's the free end of the construction elevator that can't satisfy the roof. As long as they can set up effective adhesion measures, they can also get on the roof.
Q:Elevator installation approach, need to give the total package (inspect) what data, come a master to answer the detail point
Supplement: Component members: project manager, safety personnel, inspectors, field director, technical director, foreman, elevator operation (mechanical, electrical installation and maintenance) welders, electricians, scaffolder, etc. The subcontract unit project manager shall have a certificate of construction, and special work shall be given the special work certificate. If the special work certificate is outside the province and province, the construction committee of the construction site should be put on the record.
Q:How is the construction elevator installed
Construction elevator installation 1) the location of the elevator depends on the condition of the site and the equipment, so as far as possible, stay away from the overhead line and keep the safe distance specified. When the elevator is running, there is a lot of danger and should be avoided. 2) the order of installation is: 3) place the chassis on the base and the base pre-buried bolt, and the platform is placed on the chassis, and the basket is placed in the middle of the chassis. 4) to install the standard section, each installation of two standard sections (usually less than 8m) to be temporarily fixed. The wire rope shall be used for the use of the temporary cable, and the joints and supporting points shall be bolted and not tied with the lead wire. 5) the installation should alternate between the two columns. Node bolt specification must according to the aperture matching, not packing, found that the aperture position at the time, can not arbitrarily expanding, more can't to lead wire bundle, instead to avoid loose node deformation. 6) when installing the standard section, pay attention to the vertical degree of the guide, and the line of the guide line should not appear in the line of folding and too big clearance to prevent the collision from running. 7) when construction site conditions permit, it can be assembled on the ground and then hoisted on the whole to reduce the height of the work. Due to the design of the frame, the stress condition of the construction is only considered, so before the whole moving up, the counter can be temporarily strengthened to enhance the bending capacity of the nodes.
Q:How many guides are in the construction elevator
A guide frame on each side of the construction elevator, which is formed by using the section of the standard section in section 1.
Q:The maximum allowable deviation of the vertical is the vertical degree when the construction elevator is installed
The maximum allowable deviation for the installation of the elevator rail frame is the following: The height of the elevator rail is less than 70 meters, and the vertical deviation should not be greater than one thousandth of the height of the guide frame. 2, the guide frame height is greater than 70 meters is less than or equal to 100 meters, the deviation is less than or equal to 70 mm. 3, the guide frame is larger than 100 meters is less than 150 meters, the deviation is less than or equal to 90 mm. 4, the guide frame is larger than 150 meters is less than or equal to 200 meters. The deviation is less than or equal to 110 mm. The guide frame is greater than 200 meters and the deviation is less than 130 mm.
Q:Is the construction elevator the same as the construction elevator
Construction lifter and building construction elevator, manned cargo construction machinery is a frequently used in construction, because of its unique enclosure structure make it take up both comfort and safety, construction lifter is usually used with tower crane on the construction site, the average load in 1-3 tons, running speed is 1 to 60 m/min. There are many kinds of elevators in construction, there are no two kinds of weights and weights in the way of operation, and they are controlled by manual control and automatic control. You can also add inverter and PLC control modules as needed, and also add floor calling devices to the peace layer. The structure principle and characteristics of construction lifter: construction lifter for meet the needs of the lean construction bridge, chimney, etc, it according to the building shape, install the guide frame tilt, and hanging basket level, along the inclined guide plane running up and down.

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range

Send your message to us

This is not what you are looking for? Post Buying Request

Similar products

New products

Hot products


Related keywords